Key takeaways
- Handover is the last moment you hold leverage: the final payment and, for a purchase, the transfer at the Land Office usually depend on it.
- Ask for the documents before the visit: as-built drawings, warranties, equipment manuals and the engineers' sign-offs.
- Inspect room by room, and have the contractor run the tests in front of you: air-conditioning, electrics, water, pool, home automation.
- Write every defect in a numbered, photographed snagging list, signed by both parties, with a date for each correction.
- Do not sign anything on key-handover day if you have not had time to check everything: ask for a written list of reservations, with deadlines for clearing them.
Handover is the day a villa or condo becomes yours in practice. It is also the last moment you have real leverage: until the final payment is made, and until the property is transferred at the Land Office when you are buying, the developer or contractor has every reason to fix what is wrong. Once you have accepted the keys without reservations, each defect becomes a discussion.
This guide explains how to prepare a handover in Phuket, what to inspect, which tests to ask for, and how to write a snagging list that actually gets the defects fixed. It applies to new villas, condos bought off-plan and renovation projects.
The three defects we find at almost every handover
Here is what Philippe Lanery finds at almost every handover in Phuket:
- Water and damp. This is the most frequent problem: badly executed waterproofing in bathrooms and terraces, falls that do not drain properly, leaks that only show up in the first rainy season. A waterproofing test (running water in the shower or on the terrace for a day or two) often reveals what a dry visit does not show.
- Electrics. Badly wired sockets, missing or doubtful earthing, insufficient circuit breakers, and light fittings or air-conditioners not connected properly. Because air-conditioning is essential in Phuket, its installation (condensate drainage, dedicated supply) deserves particular attention.
- Equipment and corrosion. Water heaters, insect screens, taps and outdoor hardware are often missing or of poor quality. Salt air quickly attacks ordinary steel, so check that fixings and doors are stainless steel or treated for the seafront.
Why handover is the moment that matters
Three things usually happen at handover: the final payment is released, the warranty period starts, and for a purchase the ownership transfer follows at the Land Office. Each of them reduces your ability to obtain corrections. That is why the snagging list must be complete before you sign, not after.
Check with your lawyer what your contract says about handover: who signs the handover report, what happens to the final payment if reservations are open, and how long the contractor has to correct them. Those clauses are only useful if the list of defects exists.
Before the visit: the documents to ask for
Documents to request before handover
- As-built drawingsIncluding the electrical and plumbing layouts: you will need them for every future repair.
- Engineers' sign-offsStructure and building services, signed by the engineers who designed them.
- WarrantiesWaterproofing, roofing, air-conditioning, pool equipment, pumps, solar panels: who installed what, and for how long it is covered.
- Equipment manuals and access codesAir-conditioning, water treatment, home automation, cameras, gate. Codes left with the contractor are a common problem.
- Certificates and test reportsAny test the contractor has already carried out (pressure tests, electrical tests), with dates.
The visit, room by room
Plan the visit in daylight, with time. A villa cannot be inspected properly in thirty minutes. Bring the drawings and the specification annex of your contract: you are checking that what was delivered matches what was written.
Water and waterproofing
- Bathrooms: slope of the shower floors towards the drain, silicone joints, signs of water under the tiles around the shower tray.
- Terraces and balconies: water flows towards the drains, not towards the doors; edges and upstands are sealed.
- Windows and sliding doors: seals, drainage channels clear, no stains on the frames or the walls below.
- Roof: if accessible, standing water, cracked membranes, poorly sealed outlets.
Finishes
- Tiles: tap them gently. A hollow sound means poor adhesion, a defect that gets worse with time.
- Joints, paint and plaster: cracks, stains, paint applied on damp walls.
- Doors and joinery: they close without forcing, locks work, no gaps at the frame.
Building services
- Electrical board: labelled circuits, earthing and residual-current protection present. The test itself is done by a licensed electrician.
- Sockets and lighting: every point works, outdoor fittings are rated for outdoor use.
- Air-conditioning: each unit cools, condensate drains away correctly, outdoor units are fixed and accessible.
- Water: pressure, hot water at every tap, drains empty quickly, no smell from the drains.
Outdoor areas and pool
- Pool: water level stable over several days, equipment room dry and ventilated, pumps and filters running.
- Decks and paths: fixings, slopes, no standing water after a rain shower.
- Drainage and landscaping: water leaves the plot, retaining walls drain.
The tests to have carried out in front of you
Looking is not enough: equipment must be running. Ask the contractor to run each installation during the visit, and note the result in the handover report.
| Installation | What to ask for |
|---|---|
| Air-conditioning | Every unit switched on, cooling checked in each room, condensate drains running |
| Electrics | Every circuit switched on, residual-current devices tested by the electrician |
| Water and drainage | All taps and showers run at the same time, drains emptied, hot water at every point |
| Waterproofing | Run water in the shower or on the terrace for a day or two, then check for leaks |
| Pool | Pumps, filtration and lighting running; level marked to check for loss over the following days |
| Home automation and security | Each scenario, camera and access tested; codes handed over |
| Solar panels | Production visible on the inverter or the app |
What a developer often tries to have signed too quickly
According to Philippe, these are the three most common traps on key-handover day:
- A handover report without detailed reservations. You are asked to sign a document where defects are barely listed, or grouped under “minor reservations”. Once it is signed, it becomes harder to claim for faults, and the warranty period may start from that date.
- A general discharge. Some wordings say the buyer accepts the property “as is” and waives any claim. Read carefully what your signature commits you to.
- The final payment tied to the signature. The developer may present the final payment as a simple formality, when it is what gets the reservations cleared. It is better to negotiate an amount held back (a “retention”) until all the reservations are fully cleared.
In Thailand, the transfer of ownership and the management or condo-fee contracts may also be presented at the same time. Take the time to read them, especially for a condo, where the juristic person that manages the building and the common charges matter a lot.
Writing a snagging list that gets defects fixed
A snagging list is only useful if it cannot be disputed. Each defect should be numbered, located, photographed and described in one sentence, with a deadline for the correction. Both parties sign the list, and each item is signed off again when it is fixed.
| No. | Location | Defect | Photo | Deadline | Fixed |
|---|---|---|---|---|---|
| 1 | Master bathroom | Water stays on the shower floor, slope towards the drain to be corrected | Photo 1 | Date | Signature |
| 2 | Living room, sliding door | Seal missing at the bottom right corner | Photo 2 | Date | Signature |
| 3 | Terrace | Hollow tiles near the pool edge | Photo 3 | Date | Signature |
Keep the list with the documents of the property: it becomes part of its history, and it is the first thing a future buyer or insurer will ask about. Every project we follow ends with a digital handover book that includes it.
Holding back the final payment
The final payment is your strongest lever. Many contracts allow part of it to be retained until the reservations are cleared; others say nothing, and then everything depends on negotiation. Read the payment and handover clauses with your lawyer before the visit, so you know exactly what you can hold back and for how long.
Philippe recommends negotiating a retention: an amount held back from the balance until all the reservations are fully cleared, with deadlines and late penalties.
Buying from abroad: handover through a representative
Many buyers in Phuket live abroad and cannot be there on handover day. The visit can be done by a representative who inspects, asks for the tests, writes the snagging list and shares photos and video with you. You decide, and sign, with the same information as if you were in the villa.
The power of attorney: written and precise
A foreign buyer cannot own land outright (freehold) in Thailand. They usually buy a condo, within a quota of units held by foreigners, or go through a local structure. The representative therefore needs a written, precise power of attorney, drafted in Thai and, if possible, in English.
- The document is generally signed before a notary or at the Thai consulate in the buyer's country of residence, then authenticated. Check whether an apostille is enough or whether consular legalisation is required, because the requirements have changed.
- Limit the power to the acts that are needed: receiving the property, signing the handover report with the reservations added, paying the balance against delivery of the keys, and signing the transfer at the Land Office. Avoid a general power of attorney, which would give the representative too much latitude.
- The representative should be a trusted person, preferably a lawyer independent from the developer, and not a contact supplied by the developer.
Handover from a distance
Before the date, ask the developer for the draft handover report and its annexes, several days in advance. A representative on site (or an independent expert, an architect or an inspection firm) visits the property, draws up a written and photographed list of defects and sends it to the buyer. The reservations must be listed one by one, with a deadline for clearing each and an amount held back until all are cleared.
Amend the developer's form
Do not sign the standard form as it is. Ask for the document in writing and annotate it, in particular on these points:
- The reservations are annexed in detail, not summarised under a general mention.
- Handover does not waive hidden or later-discovered defects, and the warranty period is stated.
- An amount is held back from the balance until the reservations are cleared, with deadlines and late penalties.
- The buyer or their representative can come back for a check visit.
- Any general discharge or “as is” acceptance clause is deleted or strictly limited.
- The condo documents and management fees are handed over and read before signing.
Frequently asked questions

Philippe Lanery
Founder & Owner's Representative, P&A Consulting
Philippe built and ran construction companies in Monaco and France for more than 30 years: luxury residences, palaces, casinos and hundreds of commercial sites. Based at Royal Phuket Marina, he now works exclusively for owners.
Sources
This article is general information, not legal or tax advice. Ownership structures, titles and permits must be checked by an independent Thai lawyer. Technical checks are carried out and certified by the relevant contractors, engineers and inspectors; P&A Consulting reviews the evidence and advises the owner.